WASHINGTON—The Supreme Court on Tuesday removed a hurdle to the construction of a natural-gas pipeline through Pennsylvania and New Jersey, ruling the pipeline developer could invoke the power of the federal government to take state property needed for the project.

The court, in a 5-4 opinion by Chief Justice John Roberts, rejected New Jersey’s challenge to the actions of the PennEast Pipeline Co., a joint venture of several energy companies that aims to build a 116-mile interstate pipeline.

The Federal Energy Regulatory Commission authorized the project and, under the Natural Gas Act, that approval allowed the company to use federal eminent domain power to take possession of the land, if necessary.

PennEast said it was able to negotiate rights of way with most property owners, but went to court in its bid to take dozens of parcels of land—with compensation—in which the state of New Jersey holds a property interest.

Write to Brent Kendall at [email protected]

This post first appeared on wsj.com

Leave a Reply

Your email address will not be published. Required fields are marked *

You May Also Like

Adele praises influential women after being honored at THR’s Women in Entertainment gala

BEVERLY HILLS, Calif. — Adele paid homage to the many women —…

World carbon dioxide emissions increase again, driven by China, India and aviation

DUBAI, United Arab Emirates — The world this year pumped 1.1% more…

Supply chain shortages made farm equipment scarce. Could the John Deere strike make things worse?

Joel Everett said he was astounded when a lightly used 2009 John…

Biden’s dog Commander involved in 11th reported biting incident in past year

WASHINGTON — President Joe Biden’s dog Commander was involved in another biting…