Hinkley Point C – the nuclear power station being built in Somerset – is set to be delayed, and costs are likely to be £500million more than previously thought, according to the energy giant behind it.

EDF said ‘significant progress’ has been made on the site, near Bridgwater, despite the pandemic, but previous cost estimates of £21.5billion to £22.5billion have been revised up. 

It is now expected to be in the range of £22billion to £23billion and the start of electricity generation from Unit 1 is now expected in June 2026, and not the end of 2025.

Expensive: How the Hinkley Point C nuclear power station in Somerset will look. It is expected to be completed in June 2026

Expensive: How the Hinkley Point C nuclear power station in Somerset will look. It is expected to be completed in June 2026

Expensive: How the Hinkley Point C nuclear power station in Somerset will look. It is expected to be completed in June 2026

Before the previous costings of £21.5billion and £22.5billion, the estimated price of the project had been £20.3billion. 

Original estimates had been £18billion. Once completed, it will generate electricity for around 6m, or 7 per cent, of the country’s homes.

EDF said the delay and rising cost mean the expected rate of return from its investment will fall from between 7.6 per cent and 7.8 per cent to between 7.1 per cent and 7.2 per cent.

A delay of nine to 15 months for Units 1 and 2 would cost around £700million and knock the rate of return by a further 0.3 per cent.

The Hinkley site reached a major milestone last summer, with EDF completing the 49,000-ton base for the second reactor on schedule, less than a year after completion of the first reactor’s base in June 2019.

Completion of the second reactor base benefited from experience gained on the first unit, which led to significant increases in productivity.

EDF said this will benefit the proposed project at Sizewell C in Suffolk, where a deal is being negotiated with ministers for a site that could generate enough electricity to provide 7 per cent of the UK’s energy demands.

#fiveDealsWidget .dealItemTitle#mobile {display:none} #fiveDealsWidget {display:block; float:left; clear:both; max-width:636px; margin:0; padding:0; line-height:120%; font-size:12px} #fiveDealsWidget div, #fiveDealsWidget a {margin:0; padding:0; line-height:120%; text-decoration: none; font-family:Arial, Helvetica ,sans-serif} #fiveDealsWidget .widgetTitleBox {display:block; float:left; width:100%; background-color:#af1e1e; } #fiveDealsWidget .widgetTitle {color:#fff; text-transform: uppercase; font-size:18px; font-weight:bold; margin:6px 10px 4px 10px; } #fiveDealsWidget a.dealItem {float:left; display:block; width:124px; margin-right:4px; margin-top:5px; background-color: #e3e3e3; min-height:200px;} #fiveDealsWidget a.dealItem#last {margin-right:0} #fiveDealsWidget .dealItemTitle {display:block; margin:10px 5px; color:#000; font-weight:bold} #fiveDealsWidget .dealItemImage, #fiveDealsWidget .dealItemImage img {float:left; display:block; margin:0; padding:0} #fiveDealsWidget .dealItemImage {border:1px solid #ccc} #fiveDealsWidget .dealItemImage img {width:100%; height:auto} #fiveDealsWidget .dealItemdesc {float:left; display:block; color:#004db3; font-weight:bold; margin:5px;} #fiveDealsWidget .dealItemRate {float:left; display:block; color:#000; margin:5px} #fiveDealsWidget .footerText a:hover{text-decoration: underline;} #fiveDealsWidget .footerSmall{font-size:10px; padding-top:10px;} @media (max-width: 635px) { #fiveDealsWidget a.dealItem {width:19%; margin-right:1%} #fiveDealsWidget a.dealItem#last {width:20%} } @media (max-width: 560px) { #fiveDealsWidget #desktop {display:none;} #fiveDealsWidget #mobile {display:block!important} #fiveDealsWidget a.dealItem {background-color: #fff; height:auto; min-height:auto} #fiveDealsWidget a.dealItem {border-bottom:1px solid #ececec; margin-bottom:5px; padding-bottom:10px} #fiveDealsWidget a.dealItem#last {border-bottom:0px solid #ececec; margin-bottom:5px; padding-bottom:0px} #fiveDealsWidget a.dealItem, #fiveDealsWidget a.dealItem#last {width:100%} #fiveDealsWidget .dealItemContent, #fiveDealsWidget .dealItemImage {float:left; display:inline-block} #fiveDealsWidget .dealItemImage {width:35%; margin-right:1%} #fiveDealsWidget .dealItemContent {width:63%} #fiveDealsWidget .dealItemTitle {margin: 0px 5px 5px; font-size:16px} #fiveDealsWidget .dealItemContent .dealItemdesc, #fiveDealsWidget .dealItemContent .dealItemRate {clear:both} }

This post first appeared on Dailymail.co.uk

You May Also Like

NatWest to close another 23 bank branches

Natwest will axe 23 more bank branches before June in another blow…

Big change to train tickets planned – and it could end up costing you more

A SHAKE-UP to the way we buy our tickets could mean we…

Decimal Day 50p coin: how much is it worth?

THERE are millions of 50p coins in circulation but some are worth…

Model railways maker Hornby buoyed by online summer sales

Bumper online demand helped toymaker Hornby rebound over the summer following a…

Hinkley Point C – the nuclear power station being built in Somerset – is set to be delayed, and costs are likely to be £500million more than previously thought, according to the energy giant behind it.

EDF said ‘significant progress’ has been made on the site, near Bridgwater, despite the pandemic, but previous cost estimates of £21.5billion to £22.5billion have been revised up. 

It is now expected to be in the range of £22billion to £23billion and the start of electricity generation from Unit 1 is now expected in June 2026, and not the end of 2025.

Expensive: How the Hinkley Point C nuclear power station in Somerset will look. It is expected to be completed in June 2026

Expensive: How the Hinkley Point C nuclear power station in Somerset will look. It is expected to be completed in June 2026

Expensive: How the Hinkley Point C nuclear power station in Somerset will look. It is expected to be completed in June 2026

Before the previous costings of £21.5billion and £22.5billion, the estimated price of the project had been £20.3billion. 

Original estimates had been £18billion. Once completed, it will generate electricity for around 6m, or 7 per cent, of the country’s homes.

EDF said the delay and rising cost mean the expected rate of return from its investment will fall from between 7.6 per cent and 7.8 per cent to between 7.1 per cent and 7.2 per cent.

A delay of nine to 15 months for Units 1 and 2 would cost around £700million and knock the rate of return by a further 0.3 per cent.

The Hinkley site reached a major milestone last summer, with EDF completing the 49,000-ton base for the second reactor on schedule, less than a year after completion of the first reactor’s base in June 2019.

Completion of the second reactor base benefited from experience gained on the first unit, which led to significant increases in productivity.

EDF said this will benefit the proposed project at Sizewell C in Suffolk, where a deal is being negotiated with ministers for a site that could generate enough electricity to provide 7 per cent of the UK’s energy demands.

#fiveDealsWidget .dealItemTitle#mobile {display:none} #fiveDealsWidget {display:block; float:left; clear:both; max-width:636px; margin:0; padding:0; line-height:120%; font-size:12px} #fiveDealsWidget div, #fiveDealsWidget a {margin:0; padding:0; line-height:120%; text-decoration: none; font-family:Arial, Helvetica ,sans-serif} #fiveDealsWidget .widgetTitleBox {display:block; float:left; width:100%; background-color:#af1e1e; } #fiveDealsWidget .widgetTitle {color:#fff; text-transform: uppercase; font-size:18px; font-weight:bold; margin:6px 10px 4px 10px; } #fiveDealsWidget a.dealItem {float:left; display:block; width:124px; margin-right:4px; margin-top:5px; background-color: #e3e3e3; min-height:200px;} #fiveDealsWidget a.dealItem#last {margin-right:0} #fiveDealsWidget .dealItemTitle {display:block; margin:10px 5px; color:#000; font-weight:bold} #fiveDealsWidget .dealItemImage, #fiveDealsWidget .dealItemImage img {float:left; display:block; margin:0; padding:0} #fiveDealsWidget .dealItemImage {border:1px solid #ccc} #fiveDealsWidget .dealItemImage img {width:100%; height:auto} #fiveDealsWidget .dealItemdesc {float:left; display:block; color:#004db3; font-weight:bold; margin:5px;} #fiveDealsWidget .dealItemRate {float:left; display:block; color:#000; margin:5px} #fiveDealsWidget .footerText a:hover{text-decoration: underline;} #fiveDealsWidget .footerSmall{font-size:10px; padding-top:10px;} @media (max-width: 635px) { #fiveDealsWidget a.dealItem {width:19%; margin-right:1%} #fiveDealsWidget a.dealItem#last {width:20%} } @media (max-width: 560px) { #fiveDealsWidget #desktop {display:none;} #fiveDealsWidget #mobile {display:block!important} #fiveDealsWidget a.dealItem {background-color: #fff; height:auto; min-height:auto} #fiveDealsWidget a.dealItem {border-bottom:1px solid #ececec; margin-bottom:5px; padding-bottom:10px} #fiveDealsWidget a.dealItem#last {border-bottom:0px solid #ececec; margin-bottom:5px; padding-bottom:0px} #fiveDealsWidget a.dealItem, #fiveDealsWidget a.dealItem#last {width:100%} #fiveDealsWidget .dealItemContent, #fiveDealsWidget .dealItemImage {float:left; display:inline-block} #fiveDealsWidget .dealItemImage {width:35%; margin-right:1%} #fiveDealsWidget .dealItemContent {width:63%} #fiveDealsWidget .dealItemTitle {margin: 0px 5px 5px; font-size:16px} #fiveDealsWidget .dealItemContent .dealItemdesc, #fiveDealsWidget .dealItemContent .dealItemRate {clear:both} }

This post first appeared on Dailymail.co.uk

You May Also Like

British ‘baby shortage’ could lead to economic decline, says thinktank

Social Market Foundation suggests measures including better childcare provision to increase birthrate…

Morrisons slashes prices on 150 products – list of savings revealed

MORRISONS has slashed the price of 150 products online and in-store. The…

MG wings it! Will this all-electric convertible sports car fly out of UK show rooms? 

If you think the photos look fantastic, just wait until you see…

Domino’s to hire 8,000 drivers to deliver pizzas over Christmas

DOMINO’S is planning to hire thousands of new drivers to keep up…

Hinkley Point C – the nuclear power station being built in Somerset – is set to be delayed, and costs are likely to be £500million more than previously thought, according to the energy giant behind it.

EDF said ‘significant progress’ has been made on the site, near Bridgwater, despite the pandemic, but previous cost estimates of £21.5billion to £22.5billion have been revised up. 

It is now expected to be in the range of £22billion to £23billion and the start of electricity generation from Unit 1 is now expected in June 2026, and not the end of 2025.

Expensive: How the Hinkley Point C nuclear power station in Somerset will look. It is expected to be completed in June 2026

Expensive: How the Hinkley Point C nuclear power station in Somerset will look. It is expected to be completed in June 2026

Expensive: How the Hinkley Point C nuclear power station in Somerset will look. It is expected to be completed in June 2026

Before the previous costings of £21.5billion and £22.5billion, the estimated price of the project had been £20.3billion. 

Original estimates had been £18billion. Once completed, it will generate electricity for around 6m, or 7 per cent, of the country’s homes.

EDF said the delay and rising cost mean the expected rate of return from its investment will fall from between 7.6 per cent and 7.8 per cent to between 7.1 per cent and 7.2 per cent.

A delay of nine to 15 months for Units 1 and 2 would cost around £700million and knock the rate of return by a further 0.3 per cent.

The Hinkley site reached a major milestone last summer, with EDF completing the 49,000-ton base for the second reactor on schedule, less than a year after completion of the first reactor’s base in June 2019.

Completion of the second reactor base benefited from experience gained on the first unit, which led to significant increases in productivity.

EDF said this will benefit the proposed project at Sizewell C in Suffolk, where a deal is being negotiated with ministers for a site that could generate enough electricity to provide 7 per cent of the UK’s energy demands.

#fiveDealsWidget .dealItemTitle#mobile {display:none} #fiveDealsWidget {display:block; float:left; clear:both; max-width:636px; margin:0; padding:0; line-height:120%; font-size:12px} #fiveDealsWidget div, #fiveDealsWidget a {margin:0; padding:0; line-height:120%; text-decoration: none; font-family:Arial, Helvetica ,sans-serif} #fiveDealsWidget .widgetTitleBox {display:block; float:left; width:100%; background-color:#af1e1e; } #fiveDealsWidget .widgetTitle {color:#fff; text-transform: uppercase; font-size:18px; font-weight:bold; margin:6px 10px 4px 10px; } #fiveDealsWidget a.dealItem {float:left; display:block; width:124px; margin-right:4px; margin-top:5px; background-color: #e3e3e3; min-height:200px;} #fiveDealsWidget a.dealItem#last {margin-right:0} #fiveDealsWidget .dealItemTitle {display:block; margin:10px 5px; color:#000; font-weight:bold} #fiveDealsWidget .dealItemImage, #fiveDealsWidget .dealItemImage img {float:left; display:block; margin:0; padding:0} #fiveDealsWidget .dealItemImage {border:1px solid #ccc} #fiveDealsWidget .dealItemImage img {width:100%; height:auto} #fiveDealsWidget .dealItemdesc {float:left; display:block; color:#004db3; font-weight:bold; margin:5px;} #fiveDealsWidget .dealItemRate {float:left; display:block; color:#000; margin:5px} #fiveDealsWidget .footerText a:hover{text-decoration: underline;} #fiveDealsWidget .footerSmall{font-size:10px; padding-top:10px;} @media (max-width: 635px) { #fiveDealsWidget a.dealItem {width:19%; margin-right:1%} #fiveDealsWidget a.dealItem#last {width:20%} } @media (max-width: 560px) { #fiveDealsWidget #desktop {display:none;} #fiveDealsWidget #mobile {display:block!important} #fiveDealsWidget a.dealItem {background-color: #fff; height:auto; min-height:auto} #fiveDealsWidget a.dealItem {border-bottom:1px solid #ececec; margin-bottom:5px; padding-bottom:10px} #fiveDealsWidget a.dealItem#last {border-bottom:0px solid #ececec; margin-bottom:5px; padding-bottom:0px} #fiveDealsWidget a.dealItem, #fiveDealsWidget a.dealItem#last {width:100%} #fiveDealsWidget .dealItemContent, #fiveDealsWidget .dealItemImage {float:left; display:inline-block} #fiveDealsWidget .dealItemImage {width:35%; margin-right:1%} #fiveDealsWidget .dealItemContent {width:63%} #fiveDealsWidget .dealItemTitle {margin: 0px 5px 5px; font-size:16px} #fiveDealsWidget .dealItemContent .dealItemdesc, #fiveDealsWidget .dealItemContent .dealItemRate {clear:both} }

This post first appeared on Dailymail.co.uk

You May Also Like

How to get a free pumpkin worth £2 this Halloween

PUMPKINS are a must during Halloween celebrations, and you can currently get…

Disgruntled electric car owners have made a record number of complaints this year

Disgruntled and dissatisfied electric car owners made a record number of complaints…

‘Tumbleweed town’ fears as high street card shop with 180 stores to close another branch for good

SHOPPERS have been left disappointed after a high street card shop with…

Black Friday 2020: Best furniture bargains

Has the lockdown and the advent of Christmas had you looking at…